Ports Projects
Port rehabilitation projects, including berths and infrastructure, as well as a breakwater and rubber bumpers
Rehabilitating the fenders for sidewalks (6,7,21,22) in Umm Qasr Port
Tender Number and Date: (3/Ports/2010)
Execution Period: 155 days
Beneficiary body: the General Company for Ports of Iraq.
Project Value: 1,416,000,000 IQD
The work shall include the following:
• Performing the defected steel pillars up to the level of (6,6 m) count(117).
• Manufacturing new steel pillars of hollow square cut with (36,5×35) dimensions cm and with (20 mm) thickness, count (117).
• Supplying and installing rubber pieces with the dimensions as per the schemes, count (117).
• Supplying and installing wood pieces (green hard) with dimensions (15×20) cm with a length of (6,6) m, count (117).
• Supplying fenders, count (22) and replacing fenders, count (12).
• Supplying and installing rubber fenders for the pantoon, count (8).
• Lifting the steel structure, H type with (3) m and (6) m length, count (4).

The specialized works to rehabilitate the fenders of the sidewalk no (1) Abdullah creek
Tender Number and Date: (15/Ports/2011)
Execution Period: 195 days
Beneficiary body: General company for ports of Iraq.
Project Value: 1,187,000,000 IQD
The work shall include the followings
• Supplying the material, tools, equipment and manpower to perform the works of removing the rubber fenders above and under the level of sea water, count (54).
• Performing the works of supplying and installing rubber pieces as per the original model, count (54)
• Supplying fenders as back-up pieces for the installed pieces, count (26)
• Removing the damaged steel stairs and manufacturing and installing rubber stairs with the same measures, count (4)
• Maintaining the damaged concrete layer in the front part of the sidewalk and bridges and the caps of the pillars with an area of (1000 m2)
.jpg)
Specialized works of manufacturing and installing rubber fenders and rehabilitation of its steel frame at docks (2,3,4, 11) Zobair creek port.
Tender Number and Date: (2/ports/2012)
Execution Period: 195 days
Beneficiary body: General company for ports of Irag.
Project Value: 898,000,000 IOD
The work shall include the following:
• Supply of materials and workmen to remove the damaged fenders and metal lic frames and replace with an equable
• Manufacturing and installing the new metallic frames, quantity
• Supply and installation of a set of rubber pieces, quantity 29
• Maintenance of a layer of damaged concrete at the front of the port, dimensions